Paul Davis Restoration of Utah responded immediately. Crews quickly assessed the structural damage, replaced broken windows, and coordinated multiple trades to clean and restore every part of the school. Ceiling tiles were replaced, HVAC systems sanitized, and deep cleaning of walls, carpets, furniture, and contents was carried out across both buildings. A temporary playground was installed to replace the damaged one, ensuring students could return to a safe and functional environment on time.
Solution
- Immediate response to assess radiant heat and smoke damage across both buildings.
- Strategic planning and expedited material orders to meet the strict 6-day deadline.
- Broken windows were replaced to restore building security and integrity.
- Full ceiling tile replacement to eliminate smoke odor and contamination.
- Deep cleaning and sanitization of HVAC systems and ductwork for air quality control.
- Thorough cleaning of all interior areas, including classrooms, furniture, and common spaces.
- Carpet extraction and deep cleaning to restore flooring to safe, sanitary condition.
- Temporary playground installed quickly to maintain recess access for students.
- Ongoing repairs, like roof and permanent playground installation, scheduled during summer to avoid disruption..
Project Duration:
6 days
Specialty Equipment Used:
Boom lifts, scissor lifts, dumpsters, air scrubbers, duct cleaning truck mounts